51. What is the key weakness of bar charts as a scheduling tool? x6 n/ H: x! K% H
3 J/ I0 c5 q* w- H/ ]+ g
A. they are hard to understand ! K6 S, ?- s) g* ?: b. q
B. they take a long time to produce
. F$ B3 R, c: S7 Y7 {C. they do not show an inter-relationship between activities
# X& C5 D& g) v. l" n, V; \D. it is often impractical to estimate the time a particular task will take
2 A3 G$ M1 a/ t4 k6 T! a% H0 V. g2 \
- [3 _0 b; n7 Q8 [6 M% W52. Which of the following elements of a delay claim is generally the most difficult to prove? , }5 D/ M- p o* O3 q3 p
" H. J5 a: k# {! Z
A. the amount of additional cost caused by the delay, or acceleration 4 _7 d, p/ ]- t( u; m1 e) y/ [
B. duty to not interfere with the other party's performance of the contract ) h, v! ?+ _+ r, n' {
C. breach of the duty to not interfere
" ~% I( i6 z7 `. i' ND. that the breach of duty caused a delay, or a need for acceleration * _0 [( N- M# ^$ b( r
! D+ ^5 Q0 L4 A3 |1 |53. Which of the following statement is true in a standard CCDC2 contract?# n ^2 a+ q M8 M8 {
, Y$ U7 I1 }1 }1 x0 G4 j3 {A. A compensable delay is not excusable8 _! P' M2 u$ Q$ ]3 t0 s5 q6 t
B. A contractor-caused delay is compensable: C6 M: C! _4 f% q/ ]2 k8 u
C. A contractor-caused delay is not excusable9 j* R% M% |+ g% c" q
D. Critical path activities are those in a sequence that must individually be completed before the next activity can begin. |
|