埃德蒙顿华人社区-Edmonton China

 找回密码
 注册
楼主: playball

[聊天灌水] 加拿大职业工程师考试--一起切磋

[复制链接]
鲜花(0) 鸡蛋(0)
发表于 2008-12-18 22:11 | 显示全部楼层

回复 60楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
能否将您这些题目的答案也公布一下?多谢
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 16:10 | 显示全部楼层
22. Under which of the following project delivery models does the contractor not have significant incentive to reduce costs?
7 h; g- a' ^0 t) b; D  R# u
' U. K/ c# \1 e+ [: b1 NA.     alliance agreement
$ M* }) }) }( P- M7 bB.     cost-plus contract 6 C2 J2 ^8 \/ U
C.     fixed price contract 2 k& q0 g+ X2 Y: V* |/ t
D.     unit price contract 7 I) J5 J  J# b1 m
, Z' o! n  e5 j% n/ a
23. For which of the following types of contract would the scope of work clause be most detailed? 7 A8 W# e2 W8 p9 d. v
  
' @2 O3 W8 Z' HA.    unit price 5 S# |7 U5 Y& j9 w2 ~, p! U
B.    fixed price for a design-bid-build project ( \& ^2 h" K- s" f
C.    fixed price for a design-build project
# J* o6 J  a5 y$ `- `! \; c: RD.    cost-plus 0 H$ Y# z+ S2 Y. `" W2 W

, @6 s9 O: {8 q( A3 e# d5 C24. What is another name for an exclusion clause?
7 Q4 Y/ g: K9 ^8 y8 E4 Y & I; z; H$ `! j9 ~+ d
A.     escape clause
/ x) G$ O; B/ TB.    exemption clause
9 s7 S% y" j' T# i4 u1 X7 xC.    all of the above
; d1 q4 @8 g3 [9 t. uD.    protective clause
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 17:54 | 显示全部楼层

声明

原帖由 Ape 于 2008-12-18 22:11 发表
4 g7 r7 A& r6 I  }$ ~0 o能否将您这些题目的答案也公布一下?多谢

1 z/ _) t( h& N& p8 H# e& b" p; l
$ ^- ]4 J/ e1 o, d3 q( y1. 本人发帖的目的是为了帮助大家通过NPPE考试, 旨在落实到行动, 把平凡的工作做精做细, 发扬光大下;2 T7 T3 p7 d+ h6 D
0 I4 ]" z( k, g
2. 总共将有100道考试题目帖上来, 作为大家考前摸底; 如果你不能通过这套题目的话, 你还需要继续努力;
7 A/ S" S8 t- S/ Z+ i* k3 |
2 _9 d# K2 B" `* B2 T1 M# p3. 答案将在最后被帖上来, 供大家参考.% \. I9 J- t$ h6 _

. q  ?( D, t+ B# R! w: y/ I5 g4. 有的同志, 通过了考试拿到了证书的而又在网上大言不惭的, 也可以重新测试下你的水平, 达到从根本上消除你狂妄的口气.
鲜花(0) 鸡蛋(0)
发表于 2008-12-20 00:00 | 显示全部楼层

回复 63楼 的帖子

老杨团队 追求完美
非常感谢,将一直拜读下去,希望早点见到全部。不过上一次结束时是27题,这次怎么又从22题开始了?且内容同前面同题号的题不一样
8 R+ ?5 ~: S1 L2 B6 o6 m5 X
# M- @7 u3 H4 Z' h, T3 \$ W+ C# o不要在意别人怎么说,其实通没通过差距不一定很大,可能就在一两分之间,很多刚考完的人出来说心里没底,只等通知了,有一定的运气成分。当然我们还是要好好准备才是。
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 17:47 | 显示全部楼层
对不起, 序号弄错了, 不能改正了. 接着来:
% ^4 ?/ @5 u  I3 x: h( d0 D  {+ w: z
31. Strict liability can be defined as: 0 x8 f2 e4 ?: V: [4 |- J$ ~
  6 j7 I5 h$ F0 T. L8 F9 ?! R
A.    liability flowing from negligence
8 V2 @: o8 Q: |3 h1 k, dB.    liability for the fault of another * Y. ^; R5 ~9 ?( W4 a( I& O/ Q* Q
C    liability without fault
9 ]  A1 S9 Z. G! f1 {) i2 UD.    none of the above * e+ h: b6 S& g2 C/ e
! [% ~4 B* \( h8 @* H
32. Which of the following is pure economic loss?
) B( F- u. `) y( v, A
% P- s' J# @9 A/ LA.      the lost profit of a hotel after the power went out because a motorist knocked over a municipal power pole 2 R& Y1 l  e$ t! E
B.      the painting repair cost after a roofing contractor carelessly chips the paint on the walls of the house
. a! C! \% t/ [( Z( O! T' bC.      the repair costs after a cyclist's bike is damaged by a careless motorist ; k0 E7 e$ j2 k/ _' L
D.      the medical costs associated with a car accident injury  
4 e8 U9 K5 R7 x1 V; H+ h
# S6 }6 }1 k) X8 j; U! U0 k. t( t33. Which of the following may succeed as a defence to a negligence claim?
, @3 t: \# H8 Q) U8 `. B" r  L+ q0 ]4 O
A.      the victim is an illegal immigrant - Z0 I  n+ ]5 d* a. z5 V1 f
B.      the defendant met the standard of care required in the circumstances
7 H& E+ \( ]0 g: D% F: f- \C.      the tortfeasor did not intend to cause harm to the victim ' u  l3 C2 A0 o. H  ^( m
D.      the victim is far wealthier than the tortfeasor
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 23:09 | 显示全部楼层
34. A third party to a lawsuit may be added by 4 \2 X+ H2 M$ V3 D

7 }3 l0 v$ G- A9 e9 s# ~A. either a plaintiff or a defendant, F6 D- d8 j7 y% a7 l
B. plaintiff
+ g% A4 v# b1 e, pC. defendant# T5 v1 U- [+ Z8 m: q% C- Q: |
D. none of above
8 F3 G$ @- H. S3 d+ i, A1 P: X2 `0 Z3 i  j0 ?4 t* N- T2 E5 z, I, A
35. Limitation periods are defined: 0 [7 w9 |0 @! S1 K
) f9 T) u: b; |0 J) m& F$ ?
A.      by the courts as part of the common law
# I  i& n( N3 Q3 |/ N% dB.      only by federal government legislation ! T' P+ d2 i/ {8 d* C: F4 k
C.      only by provincial government legislation 9 E' Q( F7 W' @. g9 o
D.      by federal or provincial government legislation, depending on the subject matter of the limitation period
' y. X2 ?6 Y/ i: n( y1 m2 i; S3 d2 D, ^2 @; A0 X
36. If a plaintiff was 30 percent responsible for his or her own loss, damages will be reduced by 30 percent. What name is given to the doctrine that imposes this reduction? $ s& Q% k( @1 D/ D6 U! l
     7 X6 E. C& m+ @" a6 {% w. E2 Y
A.     joint liability
$ ]. M- z1 T2 x- ?B.     joint and several liability . b/ b* ?7 {' G) h" ]- X3 N$ p) e
C.     several liability ; U; u0 e9 Y& U3 k4 J3 S8 y8 |
D.     contributory negligence
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 14:31 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
37. which of the following is not a pleading?
: {, F# e& }: g5 c" q) O2 Q6 A4 b8 g# H* m& m
A. A reply
( P. _; I2 b1 x$ O9 M0 c/ WB. A statement of defence0 J6 j: c5 X+ b2 a7 r1 J
C. Discovery of documents
* A  F) C& [2 s! L6 l) \D. Interrogatories5 A3 G* p6 O1 U- N
1 `  E8 t/ }7 n
38. What documents do judges examine prior to the commencement of a lawsuit?1 F- G' t) ]9 Y1 A; H
& [$ o4 \4 G$ l- G' ]8 ~
A. The statement of claim* [( f$ F5 Y* B. B
B. correspondence between the parties
% i. ^9 p3 o" X; v4 zC. photographs
8 o& D# a5 r: e' D( b( h/ XD. settlement offers
* [  p" h" T0 N4 W7 v* P4 Q5 L9 a( q; b- _; Z
39. Which is generally the least voluntary method of dispute resolution?
* x7 m$ x6 y5 Q8 T. w* X) b     
8 x9 s/ G6 t2 B$ k4 ?" O. IA.  litigation
+ B/ c3 Z7 C  P4 J; X( U3 e0 D+ tB.  negotiation
; c4 y# p6 V& \" H0 eC.  mediation   W: o/ {! c# j2 u" A
D.  arbitration % [% n# R: ]( f$ G  o. Q

0 J+ J( i) ]$ p. Y& g40. Which of the following methods of dispute resolution offers the advantage of privacy?
* f! E) N% {' ?. \# q# |     
( E& W2 P2 E* G; _' d1 RA.  arbitration - Y+ u: g4 D3 q: J4 v8 V0 B
B.  mediation ' f4 Z2 Z  o6 R0 h7 O
C.  negotiation
) l- k4 U: X, ?8 M8 ZD.  all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 21:05 | 显示全部楼层
41. Which of the following may require further design work by the consultant relatively late in the project? : O2 N8 Z+ N6 g
    9 f9 [% }( C  @  ^1 t6 a8 g: @& ?
A.  contractor error
  ~. t& M- s4 c# o' e, n6 ?B.  tenant requests
9 d9 E. s; z0 t# SC.  unforeseen conditions , Q# s2 m1 ^$ O9 @9 x. ?
D.   all of the above : K. Z1 h4 j3 ]

' C( Q; q6 [. b0 ^42. which of the following is not a contractual risk allocation provision?3 E2 s9 T4 m8 X; k, k8 ?1 G1 t

& ?5 _* x) `7 n* v( \  DA. An insurance clause
+ v0 T' ~2 e7 }B. An 'unforeseen conditions' clause7 l4 c  j0 t( a: @; Q! {) |6 U
C. A pay-when-paid clause
) R: G, `" s9 b; ?7 qD. none of the above
鲜花(0) 鸡蛋(0)
发表于 2008-12-21 23:33 | 显示全部楼层

回复 68楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
感谢。# \" r  N3 u2 u% R9 V" T) I
这些是以前考过的真题吗?, u. z; ]( ^: S9 p* V
请继续
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 11:18 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
43. Which of the following may result in loss of insurance coverage? ; c4 t0 h$ x6 B

: B5 n" b0 e' o5 k0 S& @, pA.      failure to comply with the notice provisions
% F5 K1 u, \( p. WB.      lack of insurable interest
' R9 ?; ^  X7 c8 UC.       all of the above ; Y8 e& t) `0 H* i8 m
D.       material non-disclosure
$ f8 Z3 f6 ]  `: H
4 e& |( L: x2 R/ Y5 d44. Which of the following is true?
1 U- M; _1 c, z; c0 g/ D1 E+ K. U6 E) G4 w( g$ b0 k( A; D8 u( l
A.      professional liability policies are normally claims-made policies
  {! W5 h; b( kB.      a claims-made policy covers liability for events that occurred in a specific time period  
" g; a2 t0 u/ v6 x& }6 ]C.      property insurance policies are either claims-made or occurrence policies 4 K+ g4 N1 U. m9 \7 A6 \7 ]
D.      none of the above
大型搬家
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 14:11 | 显示全部楼层
45. which statement is true in the following:
- Y2 I$ `; C6 b0 i3 W' J% z* k0 r  y% p, ?- d1 F& I
A. Sub-subcontractor qualify as a claimant under a standard form CCDC labour and material payment bond;
# V) L2 _" l! F8 C9 a' qB. The limitation periods available to the contractor may not be available to the surety;
" t' Y7 q3 H8 ~- Z8 `: GC. The limitation periods available to the surety may not be available to the principal;% `8 F, [0 \2 d$ |
D. labour and material payment bond is not a one-tier bond.* C4 b! W4 @4 C2 c; e2 C
2 r; O5 ?( K" o; o" z% _
46. Who may be an obligee under a bonding contract? 8 x" p% Q" _6 W% r) W: K9 J9 t
      
  e! S. m" P# u* s2 _9 AA.  the general contractor
7 X1 G4 U8 b' KB.  a private owner & G3 T, J1 p/ O8 ?' l2 m
C.  the government 5 Y7 W* a  B5 |2 U
D.  all of the above 7 T, K: n$ L$ N+ |5 R% \

+ R8 f) B% z' U+ p# F! z47. A bidder bid $80 and then refused to enter into a contract with the owner. The other three bidders bid $88, $90, and $100. The owner accepted the $90 bid. The face value of the bid bond was $9. How much is the surety required to pay the owner?  
# d& C* z/ X4 T    " H' S4 o% m  S  M
A.  $20 & _* l$ E5 U$ G+ l+ B, R. w
B.   $9   g( _7 S$ ]# W/ T0 z
C.   $8
; q" L6 n9 V: X% I# o4 pD.   $10
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 09:58 | 显示全部楼层
48. Which parties may be potentially liable for a breach of trust under a Construction Lien Act?5 ^. I% g. P7 `9 G" h( ~& A9 J
& R$ Z( g, T  ~4 g) X
A. Owner, B& E( c! ~* {  P
B. contractor
/ e( s8 [4 k. o; J9 ZC. worker
* N1 x# s5 a$ b0 Z6 z8 DD. material supplier
% p" a0 Q+ ~1 s0 j7 g2 C2 C8 f  }# t* `
49. Against what property does the lien holder have a cause of action? 6 ?. o/ ?( V1 [* L5 r
      
8 a2 k6 ]7 y4 e. Z( `, ^& GA.    the interest that the party the lien holder contracted with has in the property on which the work was done - F$ B  }% O! p% f6 P+ g
B.    the property owned by the party the lien holder contracted with
# l1 B8 \: m$ N; I+ U8 Q/ F4 VC.    the property on which the work was done & f$ b8 Z; [9 k( h; O( N5 n
D.    none of the above 5 B4 ?0 h7 r/ @5 g4 }. |6 v3 j
8 ~; l" v2 [' c  A" Z7 T4 n
50. An owner providing substitute security for a lien is, in effect:  5 {8 {2 S0 W- v* ?) H- k0 `
     & O& K# r  x' N+ w  u  \
A.  reducing his chances of having to pay out on the lien
- F- d& I* c! E# Z  q6 `B.  not changing the likelihood of having to pay the lien amount
$ M$ ]: b- \3 o" T! q$ u3 ?C.  admitting liability for the lien ! d& u( o4 @0 F' q; s
D.  none of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 13:59 | 显示全部楼层
同言同羽 置业良晨
51. What is the key weakness of bar charts as a scheduling tool?
! y" m' [/ E/ `7 ~& r  n5 t      # q7 e2 G& Z: F+ S
A.  they are hard to understand # K1 r' l, h1 j1 ?3 ~2 }
B.  they take a long time to produce
6 _& V) f5 X$ _( CC.  they do not show an inter-relationship between activities
+ Q& X: h% E! \. _, D2 ~D.  it is often impractical to estimate the time a particular task will take
: V; i/ Y4 E$ Z9 a4 F( K- x7 ]" Q. t( d3 [
52. Which of the following elements of a delay claim is generally the most difficult to prove? . K/ y( l  A3 ^7 G$ x2 l
      ' M5 r" J$ t% m' ~" N% g
A.  the amount of additional cost caused by the delay, or acceleration
3 F1 @+ S# [  u9 ?. _" [9 DB.  duty to not interfere with the other party's performance of the contract
; x$ A+ K  u! x5 i. LC.  breach of the duty to not interfere 6 ^( d4 @" M/ V" P
D.  that the breach of duty caused a delay, or a need for acceleration
- T9 t1 G5 `3 Z, b6 i2 S+ t0 g- }6 D
5 T- v; \. ^. ]' c53. Which of the following statement is true in a standard CCDC2 contract?. Z& K% F( y2 j1 ^0 _+ X$ N! G

8 O& v1 u5 b# a2 r+ A- ]* e6 X" zA. A compensable delay is not excusable
- k1 w" D$ Q  Q* ZB. A contractor-caused delay is compensable
, s# i, o+ O6 i; C; A) gC. A contractor-caused delay is not excusable/ D/ b3 c- R; w- |  Q" C
D. Critical path activities are those in a sequence that must individually be completed before the next activity can begin.
鲜花(0) 鸡蛋(0)
发表于 2008-12-23 21:13 | 显示全部楼层

回复 73楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
good job. a lot of questions for practice laws.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-24 22:35 | 显示全部楼层
54. Which of the following is not true regarding an employer-dependent contractor relationship?
* B; c  }, x! e! y4 h/ R2 o: l% ?  U      
$ }8 N1 z# T. c! _" x% oA.  the contractor may use his or her own tools * Q7 E% E- R! t) t" u( ?1 S9 }
B.  the contractor is generally not trained by the employer
& X! l7 V8 b' C- x0 @# x- f3 g0 qC.  the contractor will generally set his or her own work hours ( [4 W- V; w4 y. L
D.  the contractor is generally economically independent from the employer
4 x2 @: X1 p+ g/ {2 \# d2 j0 ^% b/ u5 f+ F6 O# f! V
55. What term describes the situation in which workers are required to pay union dues but not compelled to join the union?
, G7 R( x; l! `$ U3 Z" L     5 @' c3 z6 d* J
A. rand formula
7 {6 Q5 _0 w" U( xB. union shop
: ?* J9 f5 {( k2 m! EC. closed shop
7 Q) ?9 o% a" j0 C; h, dD. open shop 2 T5 v, ^7 E$ c- n8 p

. _. C/ D9 ~+ a% r7 G/ V9 T" `56. Which statement is true of an employer under a typical collective agreement?  |7 L1 s+ K2 s2 m
2 E! \2 s. A" w4 @# J/ c% a& v) q
A. The employer cannot terminate an employee under any circumstances;
0 y( E( T' ]$ U! [3 _& J$ fB. The employer can only terminate an employee if he gives reasonable notice;" k: a( x3 P; B3 N1 S% B. _) _
C. The employer can not lay off an employee because of a downturn in business;- q$ M3 o7 p5 B4 J$ I
D. none of the above.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 12:10 | 显示全部楼层
57. Which of the following would likely be confidential information of a contractor, which a construction manager going to a new job should not share with his or her new employer? * P2 E5 C3 k8 `) V! Q3 o1 ^8 \
     ; u/ p) D6 F- N7 \9 G, m! o! z
A.    the price the contractor pays for reinforcement from the major reinforcement supplier in town 4 N+ I" z& H* J8 f: X
B.    the names of the major concrete suppliers in town + m5 R  T7 K1 _1 J7 ?
C.    the dates on which the electrical trade closes down for the Christmas break
2 V0 k* }! ^5 G0 e, k2 Y% t7 wD.    the date on which tenders are due for a large bridge construction project
! h/ P" u4 q5 F% G9 b5 A ; ^+ d9 K* ], u4 J' {/ a
58. Which of the following suggests an employment relationship rather than an independent contractor relationship?
8 w+ }. K: c# |! {5 e     
0 }5 g& h: a. B! d# |, qA.    the person performing the work provides all of the tools and materials . [! d7 X8 K% n6 }
B.    the work is done when it suits the person performing the work 6 n: C2 F7 U$ C3 T$ u2 U; b
C.    the employer provides detailed instruction on how the work is to be done
' g0 ?7 _; W( ^/ {  h1 MD.    the rate for doing the work is negotiated for each portion of work
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:12 | 显示全部楼层
同言同羽 置业良晨
59. Zoe is a software engineer and is driving from her office to a client's office. Zoe's car is hit from behind by a polic car. Who can Zoe successfully sue?, K# x, }+ X- T% M

8 r, o- w3 a9 S! X0 _0 C: WA. Her employer0 g  K+ C7 s8 ?8 W. I% b' x6 R
B. The police officer's employer2 ]. X9 k, w& P2 M( I6 e9 u  g+ v* E
C. The police officer
) R, P8 A2 h7 J: e# AD. None of the above
  e; U( K) Z9 g; @* R) \# L9 S! R- a) b* q: k, ?
60. Which of the following is true regarding occupational health and safety? 2 G, t+ ?2 Q* X- }+ t/ O
   
) y6 U; H; j! H& [' S7 i) lA.  in each province, there are many statutes governing occupational health and safety in different contexts % b1 B$ ^4 w2 }1 ?6 w8 \  k+ h
B.  federal legislation may set occupational health and safety standards in some contexts
: i1 B$ j% H7 [" xC.  employers are required to ensure safe working conditions
: o* r; H( Y' m# {' I* M6 P$ pD.  all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:36 | 显示全部楼层

下面提供考试真题部分答案:

见附件

1.doc

23.5 KB, 阅读权限: 2, 下载次数: 14

售价: 500 加币现金  [记录]

1-12 题答案

鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 20:55 | 显示全部楼层
61. In what circumstances might an environmental consultant not have to report the findings of their investigation to the regulatory authority?
/ V; {; P& L8 x$ y     + W8 U! B; ]8 D7 [
A.  when the client, and not the regulatory authority, requested the investigation
* n5 {7 q4 z' K9 t) g% CB.  when there is a confidentiality agreement with the client ' V* t' S  y$ G* j
C.  there are no such circumstances; reports must always be disclosed . Z0 K! P2 W: N) c$ c& @" y1 R
D.  when the investigation is requested by a lawyer for the purpose of providing legal advice and there is a comprehensively worded confidentiality agreement in the consulting contract ( q! v' Y4 s0 r  Q
$ z* I$ N/ F9 Q: J1 v7 M
62. Which of the following could be an environmental offence?   G2 D0 f9 l. F6 J3 n
     ) h6 G8 G9 c+ F3 t+ Q
A.    failure to take reasonable steps to prevent contamination
9 H# [7 p: ?2 Z. eB.    failure to keep accurate books and records
* r% R  f" r- ?. EC.    failure to report contamination
  g7 O% m6 e, _6 CD.    all of the above
) c) X+ a5 Z7 G9 A ! G' G: D2 ?! V. W1 N+ Z/ P
63. If a company causes contamination, who may be liable?( C3 ~5 U  Z# p2 n2 [" M8 p
9 G* G/ g7 k6 A1 u" a. j/ Q/ E* ?
A. The company itself4 T* d3 q3 q) A1 b! P
B. the directors. ~1 k6 T; T6 d9 e
C. the prvious landowner4 s- W9 S( ]: J) Q  h# y' y
D. A and B
大型搬家
鲜花(64) 鸡蛋(0)
发表于 2008-12-25 21:19 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 22:07 | 显示全部楼层
64. Privacy legislation protects against the misuse of information about persons and organizations. Which of the following has the least protection under such legislation?
6 t. C" q4 p8 U6 Z( B- W3 O      
$ t- t9 f* N! X/ d" T, R4 {A.    private citizens
0 Z9 F* ^; m, M( F$ mB.    partnerships
$ C( v- \5 l! ?: PC.    trade unions ' G4 D/ m% p# D; B. C# w
D.    corporations

Because corporations have limited liability.doc

23.5 KB, 阅读权限: 2, 下载次数: 11

售价: 100 加币现金  [记录]

原因分析

鲜花(0) 鸡蛋(0)
发表于 2008-12-26 12:33 | 显示全部楼层

thanks.

同言同羽 置业良晨
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 13:40 | 显示全部楼层
同言同羽 置业良晨
65. What must a plaintiff prove in order to prove infringement of copyright on the Internet?
' E& x: Y) D0 U! M8 t      
- M/ C% `* A& H7 W+ }' DA.    that the work that was copied was protected by copyright
  x. {! [/ A- E; I% tB.    that the defendant actually copied the protected work
& G8 p) V  o# _C.    that a substantial portion of the work was copied 3 o! b! G) J4 m6 l
D.    all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:15 | 显示全部楼层
66. Which of the following is a correct statement of law?  
2 n6 B$ j, q5 F0 u2 r     
9 n' f1 B2 O3 o4 _A.  standard form contracts always contain both general and special provisions
7 b+ X% W8 S- C+ F+ G7 ^, W4 zB.  courts do not imply terms unless it is necessary to give effect to the intention of the parties / S1 n: {/ A( S* I
C.  where there is a conflict between general provisions and special provisions, the general provisions apply
* P$ A4 i* h5 s" T: \6 P7 u8 vD.  contracts cannot have supplemental conditions, all conditions must be included in one document
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:54 | 显示全部楼层

下面提供考试真题部分答案:

老杨团队,追求完美;客户至上,服务到位!
见附件

2.doc

26 KB, 阅读权限: 2, 下载次数: 7

售价: 1000 加币现金  [记录]

鲜花(0) 鸡蛋(0)
发表于 2008-12-26 15:49 | 显示全部楼层

回复 85楼 的帖子

can't open these attachments, can you help out?
鲜花(0) 鸡蛋(0)
发表于 2008-12-27 08:56 | 显示全部楼层
啥时候办班?先报个名。
鲜花(0) 鸡蛋(0)
发表于 2008-12-28 12:16 | 显示全部楼层

playball 你发的真当是好东西!

谢谢! 等着你继续发!
鲜花(0) 鸡蛋(0)
发表于 2008-12-29 12:22 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。/ w7 ~. S; Y+ z0 M9 u1 J& D
Appega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。/ c. D; C5 k' J/ |$ |  `
这些题目可以帮助学习,但不是考题。( d/ g( `& ]9 [% |8 K! J5 v/ I
另外,透露考题是一种违反APEGGA的道德标准的行为。尤其是在道德考试前,每人都要签字的。
/ A; q- Q5 \) q3 [' }3 _考试并不难, 只要下一定的功夫,都能通过。) W3 v0 J9 K1 V$ Z. T! }- B6 m: S6 h
并且,通过学习,可以了解加拿大的道德观和法律(这是和中国有相当不同之处),会对每一位中国移民工程师有帮助的。
# B( m1 C, R2 J( F+ L$ D大家不要舍本逐末,为了考试而考试,忘了更重要的东西。
鲜花(31) 鸡蛋(0)
发表于 2008-12-30 09:57 | 显示全部楼层
原帖由 LAOZANG 于 2008-12-29 12:22 发表
3 y& w4 R6 i! e( t7 r看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。# O0 v6 N7 v/ X; f$ \$ m3 i
Appega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。2 \$ c' r* w& T% V- }6 j
这些题目可以帮助学习,但不 ...

: h" F0 S7 L3 F2 m, g
您需要登录后才可以回帖 登录 | 注册

本版积分规则

联系我们|小黑屋|手机版|Archiver|埃德蒙顿中文网

GMT-7, 2026-9-22 14:56 , Processed in 0.215217 second(s), 28 queries , Gzip On, APC On.

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表