埃德蒙顿华人社区-Edmonton China

 找回密码
 注册
查看: 2958|回复: 1

[招聘信息] Construction Engineering Jobs

[复制链接]
鲜花(1) 鸡蛋(0)
发表于 2007-10-18 17:11 | 显示全部楼层 |阅读模式
Engineering Positions at the Diavik Diamond Mines in the NWT.
$ d. R3 T' L$ m7 r$ @3 iPraetorian Construction Management is a Project Management firm specializing in Construction Management for the Mining Industry in Western Canada. We are seeking full time Civil and Mechanical Engineers, Field Engineers, Commissioning Engineers/Specialists and Construction Superintendents for our projects currently underway at the Diavik Diamond mines in the NWT. The project is camp based with a two week in and two weeks off site schedule. * z1 |, {7 y0 _: w7 I* W3 w
0 I; s) D2 @1 I: d' g
Projects underway at Diavik over the next two years include:
# y! V7 E- }8 hBuilding Foundations                                                        
6 @8 U; b2 f; s; y4 H4 @5 qTwo dikes
# [7 I; A3 L; V& K9 X9 k7 {Dewatering, paste and process pipelines- |7 ]5 e9 ?3 |1 u7 v# Y% \% X& Q
Process plant sustaining capital works
5 K% p4 n$ f% j3 H9 q; g) V8 e' bUnderground infrastructure support works & f' d. C* \8 {( Z8 y
Mine dry building, Main camp accommodation expansion 5 h7 T% `1 J- ]8 t- H
22.4 MW power plant,
  [1 P8 k- [) PPaste Backfill facilities including a crusher and rock fill plant
! O; J. i5 ~# p% q* T" a2 v/ W8 s/ RPaste pipelines ; G  p1 ], k3 F& @, ]8 i
Underground infrastructure including electrical, pump stations, conveyance and work shops.
: @* s# `' C7 Z" M$ f+ k
: n2 B5 g0 o  \The specific duties for Field Engineers both Civil and Mechanical/electrical:
' y; x# x/ l% D4 D% O1 zManagement of technical Queries between the construction contractors and the Design Engineers" s( F3 j6 m; h% P3 K! r
Participation with the development of Site Technical Specifications with the Design Engineers
& a6 p$ J1 j; m- B# X5 y4 bQuantity Progress monitoring of the contractors and reporting
1 i; N9 J5 z# QProgress billing monitoring and audits of contractors
4 @& M3 m/ S( `$ qConstruction schedule updates with a reporting roll up to the client’s master project schedule.
9 }5 `4 d/ U, C% N4 JParticipation in the management of the Site Safety Systems
" ^* x, F( v! U) Z7 NDirecting of Vendor representatives during the installations of equipment' l) m' ^% I8 O$ V# d. n4 h
Manage the development of construction deficiency lists prior to commissioning " U, ]9 z) U/ Y7 ~! h7 _; H4 i
Participation in the planning and execution of commissioning activities
8 |* [, d' A  e4 m+ I& B
; |* O! |. C( |: b. f) l% JCommissioning Engineers/Specialists
2 p- Z/ U, @: j  ]% ^The assembly of vendor manuals and the creation of mine operating manuals utilizing the design engineering offices resources
! F" e4 ~6 J1 f) |% M4 eThe organization and participation in the training of commissioning and operating forces4 O2 G9 {' l; R8 C% o5 R
The creation of Commissioning Procedures, plans and schedules
$ P( D1 i7 \# }6 {0 uEnsure site safety standards continue to be consistently applied during the transition from construction to commissioning.
$ ^9 r" m0 l# h" bCoordination between construction and the mine operating groups
3 W, z* }# e* ^  q1 k2 fThe management of the transition from Construction to that of an operating facility including the verification of system completion and construction deficiency completions. : Z; J2 V3 i! z1 i& |
Directing commissioning crews assembled from construction, operations and the design engineering house resources. 2 c% @+ ~0 G( G) F4 t2 ~
4 y' j+ g$ Q8 ]! u7 V, h1 X0 r
Reliability / Maintenance  Engineers & Specialists
6 F5 u1 i3 J) \# X0 XThe assembly of vendor manuals and the creation of mine operating manuals utilizing the design engineering offices resources
* [! J+ G9 o" V! fThe organization and participation the creation of equipment maintenance systems and operations.! p0 }9 ~: t. ]- W/ {
The creation of equipment maintenance standards, policies, procedures, schedules and processes.
8 Y+ C4 ]3 O/ X; {( [6 f, X5 s* ]Ensure site safety standards continue to be consistently applied during the transition from construction to operations.
* h2 @* q/ C& t. r8 a- O8 A5 VCoordination between construction and the mine operating groups
% A: e. L' n& Q6 h8 a) `6 p* S4 SThe management of the transition from Construction to that of an operating facility including the verification of system completion and construction deficiency completions.
/ `0 c* n' O2 R3 O5 L+ B, E( ]
, a. W$ @9 W6 V. Y2 B$ Y6 vUnderground Construction Superintendents
" Z- e+ j" ~6 D' S$ f0 WResponsible to oversee all construction activities in the mine underground operations
$ B4 Q: v7 U/ RCoordinate mine access and equipment utilization between construction and mine development forces.
" b' p# x; u( ]' `! lDirect contractor forces1 ~& `% a  A5 J  q
Ensure contractors safety performance is in compliance with site standards
6 {) O5 z1 @3 ^2 K) [: IMonitor schedules
- Y8 j: [  f: d' qManage field engineer resources in the monitoring of progress and reporting) H3 I# ]! ?; l4 H! A/ K+ e
Participate in the management of underground equipment utilization6 U1 C5 R! B$ ?+ I  B( T2 T
Monitor the contractor’s quality assurance and control activities. I9 @0 ?# E" o, w
Participate in the transition between construction, commissioning and turnover to mine operations at the completion of construction.  
' A! w8 P* \1 RCreate Deficiency lists between development turn over to construction and construction to commissioning/turnover.
9 p& W1 S2 \- p) i$ k
& ^) |: b0 D0 t- }( L6 v  X0 u9 RCivil Construction Superintendents
" u0 t2 {% Q& O! h+ v0 @Similar to the Underground Construction Superintendent, the Civil Construction Superintendent is responsible to oversee all construction activities in the mine surface civil operations
# r6 w% g# y% N6 X7 oCoordinate equipment utilization between construction and mine operations forces.
' z8 N, A( b( v9 J; p% M. C, RDirect contractor forces
1 @) f; w. U0 e8 b( z( G+ YEnsure contractors safety performance is in compliance with site standards
* D8 H. [' F' M" FMonitor schedules
. A0 x, v; n3 M: U2 |0 r$ i; YManage field engineer resources in the monitoring of progress and reporting
' q- x- i/ p' g* v' i2 oMonitor the contractor’s quality assurance and control activities/ P- g8 g5 p, P8 ]# q
Participate in the transition between construction, commissioning and turnover to mine operations at the completion of construction.  ! M: |* T4 O: l2 }( x. ^
Create Deficiency lists between development turn over to construction and construction to commissioning/turnover.
3 O8 x( L2 ^/ p" }, P  J" h
4 v+ V4 b" a& f+ r& K8 y3 `* WNote:, ~/ O% a3 [/ L2 a/ S- O
Individuals with a professional designation will be expected to register with the appropriate NWT professional organization.6 Y2 e! P: S3 g* F6 |( q
/ V- b3 ^3 B# y
' Q+ d* g9 |" L: ~: q2 f! h+ |+ K7 j
" c" L, q; @& I1 r# H1 [
The company provides you flights between Edmonton and the mine, and food and accommodation in the mine. You work 2 weeks and take 2 weeks off. So virtually you only work less than 6 month a year. Depending on your qualifications, your income is about 60,000 to 100,000 a year plus benefit and 8%-12% bonus. You can buy up to 3 carats diamond per year when you work at the mine at discount price (about 1/3 of retail price). Please go to www.diavik.com for more info about the mine.
2 u' f4 ?, j* T4 g* {! W; I
) {9 J/ I( {2 U0 E, a2 ]6 ?If you are interested and you have:
: ^$ \$ x' `" A5 VMin. 2 years related Canadian experience) ^5 Q3 |! ~9 A  c4 o6 |
Good English
8 \1 x  }5 f- T1 G4 p, SGood computer skills, esp. Excel/ I% f2 o9 w& T4 ~& o* i1 ?. U
Engineering degree in civil, mechanical or electrical.2 Q& w$ S2 m5 q
; y! x) ]: k0 f5 a
Or if you have qualified friends from other provinces, who are willing to move to Edmonton or Yellowknife, and they are interested, you or your friends can send resume to luckylu888@yahoo.ca. The positions are expected to be filled by Nov. 2007.
9 F% q3 j1 ?+ u- {4 H% j8 w) a+ E
) f9 A  n; W4 o, D' nThanks a lot.
鲜花(64) 鸡蛋(0)
发表于 2007-10-21 17:56 | 显示全部楼层
您需要登录后才可以回帖 登录 | 注册

本版积分规则

联系我们|小黑屋|手机版|Archiver|埃德蒙顿中文网

GMT-7, 2026-11-25 13:25 , Processed in 1.301694 second(s), 12 queries , Gzip On, APC On.

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表